Before water flows through new treatment facilities, pipes and storage tanks, there will be a lot more digging, rigging and mud and a few traffic slowdowns.
Work is continuing on $101 million of improvements to Pennsylvania American Water infrastructure, and the project will bring a variety of restrictions along Becks Run Road in the South Side and Baldwin Borough until it is completed in midsummer.
"Hopefully the impact will be a lot less than what we did last year," project manager Jay R. Lucas said.
Penn American is replacing its water intake on the Monongahela River, which draws up to 60 million gallons per day, along with a 118-year-old pump station, underground water mains and the Hays Mine Water Treatment Plant.
The project required alternating one-way traffic on Becks Run Road last summer, which produced gridlock and eventually caused officials to change the pattern to one way outbound from East Carson Street.
This season's biggest disruption will be an alternating one-way pattern, with traffic controlled by a temporary signal, at the Becks Run intersection with Parkwood Road. That is scheduled for April and May as crews dig up the intersection to connect a 42-inch main that was installed last year to three existing 24-inch pipes that will carry water to the new treatment facilities.
Alternating one-way traffic will be in place on Agnew Road near the Becks Run intersection from late February to early May while crews excavate next to the road to connect two 48-inch mains that pass under the street. The restriction will occur during off-peak hours during the daytime, Mr. Lucas said.
Demolition of the 1894-vintage pump station on East Carson at Becks Run, scheduled for late May through June, is expected to squeeze East Carson traffic into two lanes just south of the intersection. The building sits right against the road.
Work at the site of two giant new storage tanks on Becks Run north of Agnew Road has already caused intermittent lane closures and traffic shifts, which will continue.
The new intake on the Mon is nearly complete and any disruption to users of the Three Rivers Heritage Trail will be minimal as crews do finishing work and replant the area, Mr. Lucas said.
Penn American spokesman Gary Lobaugh said the company will announce details of traffic restrictions as the dates approach. Information also will be made available at www.pennsylvaniaamwater.com , click alert notifications.
This story was originally published with images that are no longer available.