Finishing work on a $17.3 million rehabilitation of the Boston Bridge will cause traffic restrictions this week and next, the Pennsylvania Department of Transportation announced.

Alternating one-way traffic will be in place from 9 a.m. to 3 p.m. Wednesday through Friday and next Tuesday through Jan. 6 for inspection and railing installation.

The two-year project is almost complete but PennDOT expects to close the bridge, which carries Route 48 over the Youghiogheny River between Versailles and Elizabeth Township, for one full weekend in the spring to complete deck resurfacing.