Short-term Interstate 79 lane closures running from Allegheny County to Washington County begin today should weather allow them, PennDOT announced.

The highway will become one lane in each direction from Washington County to a half-mile north of the Bridgeville interchange (Exit 54) from 9 a.m. to 3 p.m. and again from 7 p.m. today to 7 p.m. Saturday. Work will continue Monday through Thursday from 9 a.m. to 3 p.m. and 7 p.m. to 6 a.m., and next Friday from 9 a.m. to 3 p.m.

The work is part of a $2.6 million project repairing three bridges, sealing joints, patching concrete, updating signs, improving guardrails and making other upgrades on 3.7 miles of highway. Led by primary contractor Swank Construction Co. LLC of New Kensington, the work is scheduled to end next summer.