Mt. Lebanon's proposed $11.6 million aquatic center could die in the concept stage for lack of enough municipal commissioners' votes to approve a major share of the financing.

The possibility came to light as architects pushed last week for members of the center's planning committee to choose a layout for the buildings.

At least four of the five Mt. Lebanon commissioners would have to vote to approve a bond issue to finance the roughly $6.5 million municipal share of the project.

But two told the Pittsburgh Post-Gazette they opposed the current plan, while one favors it, one remains undecided and one declined to give his opinion.

Advertise with us

The dissenters said they could change their minds if their questions are answered and greater focus were put on the leisure pool, the fitness center and other community uses they said would make the pool financially feasible.

The school board has allocated $5.1 million for the project, which, if rejected by the commissioners, is likely to be downsized and built solely by the district on the high school campus, as previously planned.

Plans call for a joint school district/municipal swim center near the outdoor pool off Cedar Boulevard to include a 50-meter competitive pool. The center also could include a four-lane leisure pool with a graduated depth entry, a fitness center, locker rooms and seating for up to 1,000 spectators.

The plans are about $1 million over budget. The school board will not exceed its $5.1 million contribution and the municipality cannot exceed a $6.5 million contribution without a referendum.

Rob Pillar, of Burt Hill Kosar Rittelmann Associates, presented the committee last week with several cost-cutting plans, one of which calls for deletion of some architectural features, deferment of the fitness center and demolition of the outdoor pool, because guaranteeing its stability during construction would be costly.

Advertise with us

The proposal includes line items, so individual cuts could be restored. Other options, such as a broom-finish concrete deck instead of ceramic tile, could be upgraded later.

Challenges to the project include a site with limited space and parking and a goal to open the pool by the fall 2006 swimming season.

Commissioner David Humphreys supports an aquatic center and likes the idea of a 50-meter pool, but he said the only way to make it financially doable would be to have solid public memberships, which he believes require a larger, equipped fitness center and larger leisure pool.

"Deep pools always lose money," he said, unless a fitness center component can cover costs. Humphreys calculated that the aquatic center, as envisioned, would lose $1 million in operating expenses per year plus another $900,000 of annual debt service taxpayers would have to cover.

Although he said there was pressure to make a decision soon, he prefers to take another year to work out a more profitable concept. If the vote were tomorrow, he would be against the center.

Advertise with us

"I would like to see the 50-meter pool, but I'm not willing to approve it unless operations costs are going to be substantially covered," he said.

Commissioner Barbara Logan said she had too many unanswered questions to support the project now.

"I just find the whole thing troubling. And it's better to be troubled ahead of time," she said.

Logan said the proposed building was too large for the site and would change the character of Mt. Lebanon's main park. Before changing her vote to a "yes," she would require answers to a list of questions.

First, she would require a full, "detailed, realistic budget," that would include all costs, including utilities, physical plant issues, increased police use during swim meets and all sources of revenue, among other things.

Advertise with us

She also wants to know how attendance at the center would affect other nearby recreation events, such as hockey and football games and use of the recreation center. Parking is a major concern for her.

Commissioner Dale Colby said he understood why the school team and private Mt. Lebanon Aqua Club need the pool and why it could be good for the community, but that he was concerned that the current proposal may focus too much on competitive swimming and not on the other uses, such as the fitness center and leisure pool.

When he analyzes the numbers, he thinks, "Wow, this is tough to justify."

He said he remained unsure how he would vote. "I really do flip-flop. I'm going to have to make a decision pretty soon," he said.

Commissioner Keith Mulvihill understands why the planning process is tough. It would be easy to build a strictly competitive facility or easy to build a strictly leisure facility, he said, adding, "It's difficult to put them together with any reasonable amount of money."

Advertise with us

Still, he favors the project, although he agrees that it would be helpful to have a larger leisure pool and fitness center.

Commissioner Ty Ely would not comment on his position, saying he needed a few days to think about it.

The pool planning committee will schedule another public meeting for a date in the next few weeks.