The Pittsburgh Water and Sewer Authority has completed the restoration of its 146 million-gallon reservoir in Shaler, a project that lasted two years.
The Lanpher Reservoir is split into two. Work on the east cell was finished last week, following the completion of the west cell last August. Work on the reservoir began after the Pennsylvania Department of Environmental Protection ordered the PWSA to expedite three priority projects in 2017.
The DEP issued a permit to put the east cell back into service on Tuesday. PWSA split the project so the reservoir could distribute water from one half while work was being done on the other.
The restoration included replacing over 28,000 square yards of liner and cover, as well as improvements to the concrete wall surrounding the facility. The PWSA estimates the project cost $8.7 million.
“About a third of our customers get their water from this reservoir,” Will Pickering of the PWSA said Wednesday. That includes residents of the North Side and other northern neighborhoods and communities, including Millvale.
Work was originally planned to end in 2018, but delays caused by rain and winter weather caused the PWSA to ask the DEP for an extension on the mandated deadline. The revised timeline set the project to be completed by the end of June.
The last remaining project ordered by the DEP involves improvements to a micro-treatment plant in Highland Park. Once completed, the Highland I Reservoir will be back online for the first time since February 2017, Mr. Pickering said.
The Highland Park project is set to wrap up by the end of summer.