An inspection of the recently rehabilitated Port Authority bridge in Emsworth determined that contractors likely used steel braces that had been plug-welded — a process that can weaken steel — but inspectors concluded the bridge wasn’t in immediate danger.
The Pennsylvania Department of Transportation inspected the Center Avenue Bridge on Jan. 16, paying special attention to whether braces used in the $3.65 million project included welded material.
The Post-Gazette reported three weeks ago that documents showed a subcontractor may have provided steel braces that had misdrilled holes filled by a process known as plug welding. PennDOT does not allow plug welding because such heating of steel can create weak spots.
PennDOT has a contract to inspect Port Authority bridges every two years and routinely inspects a bridge after any major work. Port Authority requires its projects to be built to PennDOT standards.
“While the inspection was not 100 percent conclusive that plug welds exist on the structure, there is evidence that welding occurred,” PennDOT’s District 11 office said in a statement. The agency wouldn’t specify where the welded pieces were located but it recommended those areas get special attention in future inspections.
Plug welds were a common practice in bridge construction decades ago, but now most states prohibit them. Last year, the Delaware River Bridge between Philadelphia and New Jersey was closed for seven weeks after it developed a 2-inch gap at a 60-year-old weld site.
And in April, PennDOT will issue a contract to drill out about 650 plug welds on 13 bridges across the state and put bolts in the holes to strengthen the steel.
Port Authority spokesman Adam Brandolph said the possible sites were not “on a primary load carrying part” of the Center Avenue Bridge so no immediate action is necessary.
The bridge reopened in December after a year-long project that included replacing the concrete deck, repairing or replacing structural steel and painting.
Although no steps have been taken to change inspection practices during a construction project, Mr. Brandolph said, the agency is “looking into our options to avoid situations like this in the future.”
Ed Blazina: eblazina@post-gazette.com, 412-263-1470 or on Twitter @EdBlazina.






Comments
Welcome to Post-Gazette subscriber-only commenting community. Please review our community guidelines.