Paving was scheduled to be finished on southbound lanes of Interstate 79 through Marshall by this morning, the latest milestone in this summer's $6.9 million improvement project.

Angelo Pampena, project engineer for the Pennsylvania Department of Transportation, said work will shift to the southbound ramps starting with tonight's 7 p.m. to 6 a.m. period of traffic restrictions.

"The ramps probably won't be done until shortly after the Labor Day weekend," Pampena said. "Then we'll start resurfacing the northbound lanes and ramps."

The contractor, Lindy Paving, must keep one of the three lanes in each direction open while it works 7 p.m. to 6 a.m. weekdays. When Lindy works overnight Friday, Saturday and Sunday, two lanes must remain open each way.

Advertise with us

The two-mile project that began June 20 is to be finished sometime in October, weather permitting. PennDOT is resurfacing with a 31/2-inch thick mat of asphalt over the stretch south of Warrendale.

Prior to paving, workers replaced deteriorated pieces of the old highway to build a strong base for the new asphalt.