A contractor has sued Mercer County for $500,000 on claims that the county failed to provide adequate land survey data and ordered its workers to use materials of an insufficient quality on a misaligned bridge.

Carmen Paliotta Contracting Inc. claims the county made "increasingly unreasonable demands" on the bridge work by telling the company to fill the bridge foundations with an inadequate type of concrete, even after the pedestals were found to have settled after the start of the project in August 2001.

The county "summarily declined to evaluate, in any detail, Paliotta's concerns over settlement. Instead the county directed Paliotta to repair the structure without offering any instruction or directive on how to do so," stated the lawsuit filed Thursday.

County Commissioner Olivia M. Lazor declined to comment on the suit Friday. She said she wanted to let county attorneys review the lawsuit and respond.

Advertise with us

The lawsuit also names as defendants the Mercer County Bridge Department, the state Department of Transportation, designer Gannett Fleming Inc. and another contractor, T.W. Consultants.

Paliotta began dismantling the misaligned Oakland Avenue Viaduct in Sharon in November but work was stopped Jan. 8 by county and PennDOT personnel. A letter dated the same date stated that the county was requiring Paliotta to repair and not replace the pedestals.