Franklin Regional officials posted a 31-page document to the school district’s website answered more than 200 questions from the community on a proposed elementary school renovation and reconstruction project.
The questions, many of which were posed at a public forum last month, address 11 categories of concern, including government approvals, student safety and traffic conditions.
The school board received more feedback at its meeting Monday night.
The plan, estimated to cost from $53.7 million to $57 million, calls for an elementary campus on Sardis Road in Murrysville that includes renovating Sloan Elementary School for grades kindergarten to second grade and constructing an intermediate elementary school for grades 3 to 5.
Groundbreaking for the existing Sloan renovation is expected to occur in the fall. The bid process for the new intermediate building is expected to be complete in October.
Murrysville resident Lori Gardea voiced concern Monday night over the “great divide” between the community and board regarding the project.
Board member Gregg Neavin said he has maintained composure after being called a liar regarding the project and that it has been “heartbreaking.”
“I sit here with nine other people who have done our absolute best to become informed, who went through a process to select the people to do a (feasibility) study and have pored over this study for a long time,” he said.
“Thank you for suggesting that we act like human beings toward one another.”
David Plank of Murrysville asked the board to reconsider what he characterized as a “bad decision” to move forward with the project.
“To me, it would make much more sense to buy laptops and tablets for the students to explore the world than to go to the expense of building a library,” he said, adding that if the current buildings are properly maintained they would be serviceable and would continue to be a source for “extraordinary academic achievement.”
Murrysville resident Ed Mittereder applauded the board’s recent approval to spend $600,000 on technology upgrades that will include the addition of Google Chromebooks throughout the district.
Rick O’Mahony a paramedic and Medic One board member, said he is concerned about emergency-response access to the Sloan campus.
“During the [March 12] roundtable there were statements made that there will be traffic signals placed at the intersection of Bulltown and Sardis roads and at the intersection of School and Sardis roads with pre-emption capability,” he said.
Mr. O’Mahony said he subsequently met with municipality officials who confirmed that wasn’t the case.
The district currently is conducting its third traffic study for the project.
Parent Jesse Macpherson said he was impressed with the detail with which the board answered the community’s questions.
“I do think that the Sloan project would be an excellent educational situation for our students,” he said, adding that he learned that after enrolling his son in kindergarten, more slots needed to be added.
“Maybe that’s not a long-term trend, but I know that right now there are more people entering kindergarten than what they had anticipated slots for,” he said.
As of last month there were 191 children registered for kindergarten, compared to 132 through the same period last year.
Laurie Bailey, freelance writer; suburbanliving@post-gazette.com