A process that resembles assembling a jigsaw puzzle of uniform pieces will be used to replace a bridge on Route 30 in one weekend this spring.

The $2.4 million project will use precast and prefabricated pieces to replace the 56-foot-long bridge over Bessemer Avenue in East Pittsburgh.

That work is among 50 road and bridge projects worth an estimated $272 million that PennDOT expects to begin this year in Allegheny, Beaver and Lawrence counties.

The agency decided to use “accelerated construction techniques” on the East Pittsburgh bridge when an inspection showed only minor cracks in the concrete substructure, said Steve Cowan, spokesman for the state Department of Transportation.

Advertise with us

Replacing the superstructure using conventional methods would have forced the highway to be closed for several weeks.

Instead, all of the primary elements of the bridge are being made in advance.

For example, manufacturers will create six ”modules” consisting of two steel beams with a concrete deck precast onto them. In addition, precast slabs will be used at the bridge approaches.

During the two days the bridge is closed for replacement, crews will remove the existing superstructure and the tops of the abutments. New precast caps will be placed on the abutments as seats for the new superstructure. The beam modules will be attached using ultra-high-performance concrete.

About a month after the superstructure is installed, the bridge will be closed for a second weekend to place a final latex modified concrete overlay on the road surface. That work can’t be done until the concrete joints have cured.

Advertise with us

Brayman Construction Corp. is the contractor for the project.

Other east suburban projects in PennDOT’s orange barrel parade this year include:

• Finishing a $10.8 million project to widen Route 286 in Monroeville and Plum to add a turning lane. Remaining work, expected to be finished in June, includes reconstructing parts of Old Frankstown Road and Sagamore Hill Road as well as sidewalk and curb work on Route 286.

• Finishing a $6.98 million project to widen and add a turning lane on Lincoln Way in White Oak. Remaining work, expected to be finished in June, includes reconstruction and curb and sidewalk installation between Henderson Road and Auld Street.

• Finishing the third lane at the Oakmont end of the new Hulton Bridge between Harmar and Oakmont. The project will be done before the U.S. Open begins June 13 at Oakmont Country Club.

Ed Blazina: eblazina@post-gazette.com or 412-263-1470.