A $12.9 million, two-year replacement project at the Route 30 bridges over Electric Avenue in Chalfant and North Braddock begins today with a ramp closure.

Later in the season, all traffic will be moved to one bridge while the other is torn down and replaced. That will bring the first of two seasons of single-lane traffic in both directions, not far from where drivers faced similar restrictions during rehabilitation of the Westinghouse Bridge in 2009 and 2010.

For now, though, only the ramp from eastbound Route 30 to Electric Avenue is affected. It will close from 7 a.m. today through late April as crews do water and sewer line improvements. According to the Pennsylvania Department of Transportation, about 3,400 vehicles use the ramp on a typical day.

The original posted detour used 11 streets, but drew objections from East Pittsburgh's borough engineer, who said one of them, Linden Avenue, was unsuitable for trucks. The revised detour, made public by PennDOT today, is for traffic to continue east on Route 30 across the Westinghouse Bridge and turn right at Navy-Marine Corps Way, right at East Pittsburgh-McKeesport Boulevard and right at the Tri-Boro Expressway to return to Electric Avenue.

Advertise with us

Another possible route for low-clearance vehicles is to turn right on Yost Boulevard before reaching the closed ramp and follow it as it becomes Sixth Street, turning left on Braddock Avenue.

At a briefing this month, PennDOT officials said traffic flowed fairly well during the Westinghouse Bridge project and they expected the same with this year's construction.

The bridges were built in 1932 and are listed as structurally deficient. Other project work includes paving, approaches, drainage improvements, new guide rail, lighting and a retaining wall. The contractor is Trumbull Corp. Completion is scheduled for fall 2013.