Bigelow Boulevard is closed in both directions at Finland Street in Polish Hill after the pedestrian bridge that crosses overhead was struck by a crane Friday morning, causing severe damage to the structure.

A large tri-axle truck with a boom crane had the boom extended when it struck the bridge around 8:15 a.m., according to Pittsburgh Public Safety.

Officials with the City of Pittsburgh said that after a “thorough inspection” of the bridge, it would have to be demolished before the roadway could be reopened.

Demolition could begin as early as Friday evening and is tentatively scheduled to last one week, the mayor’s office said.

Advertise with us

Crews worked Friday afternoon to secure power lines before the demolition of the bridge.

“Our administration is dedicated to the safety of our citizens,” said Mayor Ed Gainey. “We will move as quickly as we can in order to safely re-open Bigelow Blvd, but our number one priority is to keep everyone safe, and that means taking down the Finland pedestrian bridge.”

Bigelow Boulevard is closed in both directions between Herron Avenue and the Bloomfield Bridge intersection.

Suggested detours:

Westbound from Baum Boulevard:

Advertise with us

Turn right onto the Bloomfield Bridge; continue across the bridge and left onto Liberty Avenue; continue on Liberty Avenue to Grant Street, then turn left onto Seventh Avenue to get back to Bigelow Boulevard.

Westbound from Bloomfield Bridge:

Turn left onto Bigelow Boulevard; take a slight right to continue on Bigelow Boulevard, turn right onto Centre Avenue; turn right onto Herron Avenue, which will take you back to Bigelow Boulevard.

Eastbound:

Turn right onto Herron Avenue; continue on Herron Avenue and then turn left onto Centre Avenue. Motorists who want to get to Bloomfield will turn left onto Bigelow Boulevard and those going to Baum Boulevard will continue on Centre Avenue and turn left on North Craig Street.

Advertise with us