The National Transportation Safety Board on Thursday released the first photos from Port Authority bus video cameras that show the initial, horrifying moment Fern Hollow Bridge collapsed three months ago.

The photos support the NTSB’s first conclusion released on Feb. 7 — 10 days after the bridge’s collapse on Jan. 28 that injured four of nine people who were in six vehicles on the bridge — that the bridge collapse began on the west end of the bridge, starting a rapid cascade of failures across the bridge.

That conclusion about where the collapse began was based on viewing the bus’s video cameras, the NTSB said on Feb. 7, but it did not release any photos until now.

A video frame from the rear-facing curbside camera, shows the west end of the bridge already fallen off the west abutment. Courtesy of NTSB

One of the two photos shows the very moment a forward-facing camera on the bus shows the expansion joint — which connects the bridge itself to the roadway beyond — on the east end of the bridge just starting to pull away from the roadway beyond.

Advertise with us

A second photo from a backward-facing camera on the bus’s right side shows that, at about the same time, the west end of the bridge “had already fallen off the west abutment,” the NTSB said in its update on Thursday.

The backward-facing photo taken from the video on the bus is grainy, and hard to see in the dark of the early winter morning — the bridge collapsed at 6:40 a.m. — but it shows the guardrail next to the sidewalk on the far west end has already disappeared, while part of the distant guardrail is just beginning to fall out of view, and the guardrail alongside the bus is still upright.

Video frame from the forward-facing camera, showing the opening expansion joint. Courtesy of NTSB

The forward-facing photo also reveals that when the bridge collapsed, the bus was close, maybe less than 100 feet, from leaving the east end of the 450-foot bridge.

NTSB’s update also said that its investigation looking at other bridges of a similar design, called a “rigid K-frame superstructure,” so far “has not found any evidence of widespread deficiencies” with similarly designed bridges.

The update said that both NTSB and Federal Highway Administration investigations plan to do mechanical and chemical testing on samples of each of Fern Hollow’s four bridge legs and several girder sections. They will also examine plate dimensions and weld quality.

Advertise with us

While some examinations of the bridge occurred on-scene after the collapse and during demolition as additional pieces were uncovered, some pieces were collected and are being housed in the FHWA’s research center in McLean, Va., for future testing. Still other parts collected from the site will be analyzed at the NTSB’s own materials laboratory.

“All aspects of the collapse remain under investigation while the NTSB determines the probable cause, with the intent of issuing safety recommendations to prevent similar events,” the NTSB said Thursday.

Sean D. Hamill: shamill@post-gazette.com or 412-263-2579 or Twitter @SeanDHamill