After more than three years of discussion, the City of Pittsburgh, the Pittsburgh Parks Conservancy and the North Side neighborhood have settled on a design for a new West Ohio Street Bridge that will cause minimal disturbance to the historic Allegheny Commons park.
But that project is only the first step in replacing a series of bridges that cross above Norfolk Southern tracks as the railroad prepares the area to handle double-stacked rail cars over the next few years. Park and neighborhood advocates say they hope the railroad will be as responsive to their design concerns as the city has been with the West Ohio Street Bridge.
“The key here is we’re going to get a new bridge, but that bridge is going to look like it’s been there for 100 years,” said Mark Fatla, executive director of the Northside Leadership Conference. “That’s a testament to the [Pittsburgh Parks Conservancy], the neighborhood and the city working together to balance the issues of a historic park with the needs of a modern transportation system.
“It didn’t start off as a happy conversation, but it ended up in a good place.”
Since about 1912, railroad tracks that pass through the North Side and Allegheny Commons have been sunk below ground, which minimizes the disruption that trains cause in the neighborhood and park. The goal with the bridge projects is to preserve as much of that as possible, especially within the park.
Pat Hassett, the city’s deputy director of public works, called the new West Ohio bridge “truly a community-driven design.” The initial design involved building up the park’s soil three to five feet to increase the clearance under the bridge but that would have resulted in the loss of more than a half dozen historic sycamore trees, so the group worked to reduce the effect on the park.
Read More

Susan Rademacher, parks curator for the conservancy, credited landscape architect Kara Roggenkamp of Pashek + MTR for suggesting a design that uses retaining walls rather than soil and will eliminate only two trees. Overall, the design “satisfied most of the concerns” the conservancy had, she said.
“That was a wonderful solution,” Ms. Rademacher said. “That whole process was really quite collaborative.”
In addition to the retaining walls, the bridge itself will be made from precast concrete with black metal rails and carry two lanes of traffic plus bike lanes. Short staircases will carry pedestrians from the park to the bridge deck on each side of the tracks.
The existing bridge was built with two lanes in each direction separated by a tall metal median, but half of the bridge has been closed for several years and the other half has two-way traffic. In addition to replacing the West Ohio bridge, the city will remove the long-closed Ridge Avenue bridge a short distance away.
Bids for the project, expected to cost about $4.5 million, are scheduled to be awarded March 29 and construction should begin about 90 days later.
But that’s only the beginning of railroad bridge projects on the North Side.
Norfolk Southern received a $20 million state grant in April to raise and replace bridges at Columbus Avenue, Pennsylvania Avenue and Brighton Road-West North Avenue. The goal is to provide a second route through the Pittsburgh area for double-stacked rail cars so Norfolk Southern’s system isn’t brought to a standstill by a landslide from Mount Washington onto tracks on the South Side, which happened last July.
Railroad spokesman Jon Glass said those projects are in preliminary design and won’t be ready for presentation to the city and neighborhood until sometime next year.
“These projects take time. It takes some careful planning,” he said.
The conservancy and neighborhood particularly are concerned about the Brighton-North bridge because it is on the edge of the park. The roads approaching the bridge already have a significant hump approaching the bridge, which is expected to be raised higher.
“The conversations on design for the rest of them haven’t begun,” Mr. Fatla said. “It’s always a three-way dance among the neighborhood, the city and the railroad.”
Ed Blazina: eblazina@post-gazette.com, 412-263-1470 or on Twitter @EdBlazina.