East Lacock Street on the North Shore will be closed between Federal and Sandusky streets until March 10 while a contractor fixes the second sink hole problem in two years.

Frank J. Zottola Construction Inc. began work Monday to remove the concrete road surface immediately across from the rear entrance to the North Shore parking garage. The work will involve removing some of the old fill, dumping in clean fill and compacting it before pouring new concrete.

The goal of the project is to eliminate a jarring dip that carries across all three lanes of the road, which is the link from southbound Route 28 to the North Shore parking lots and garages. The work is a few dozen feet where crews repaired two sink holes in the same block in late 2015.

Pittsburgh Public Works Director Mike Gable said three weeks ago the problems have occurred because the street was built on top of unstable fill from construction of the Interstate 279 ramps above the area. Standard construction practice at the time involved dumping debris into basements when buildings were razed and over time that fill deteriorates and caused problems for the street above it.

Advertise with us

Mr. Gable estimated the cost of the current project at $130,000. The work in 2015 cost $160,000.

Here are the posted detours:

• Outbound on Lacock Street: turn right onto Federal Street, left onto General Robinson Street and left onto Sandusky Street.

• Inbound on Lacock Street: turn left onto Sandusky Street, right onto Isabella Street and right onto Federal Street.

Entry and exit to parking lot BLUE 7F will be from Sandusky Street. Entry and exit to parking lot BLUE 10 will be from Federal Street.

Advertise with us

Any Port Authority bus routes affected will follow the posted detour.

Ed Blazina: eblazina@post-gazette.com or 412-263-1470.