Contractors working for the Pennsylvania Department of Transportation began using jacks in the repair of the Liberty Bridge on Friday morning, a process intended to realign a weight-bearing beam that was damaged in a fire earlier this month.

The meticulous operation got off to a smooth start and will continue during daylight hours over the weekend and into early next week, according to Dan Cessna, PennDOT’s executive for the district that covers Pittsburgh.

A lower compression chord vital to the bridge’s stability buckled in the intense heat of the Sept. 2 blaze and twisted a joint where several other beams come together, causing the bridge to shift one to two inches, Mr. Cessna said.

The purpose of the jacking that began Friday, he said, is to remove the twist and get the chord realigned into its proper position. Then workers will use another jack as well as heat to straighten and elongate the chord and move the bridge one to two inches into its proper position. As the jacking process takes place, the weight that the chord held up will be distributed to a temporary support system that will be removed after repairs are finished.

Advertise with us

“It’s something that’s very incremental,” Mr. Cessna said of the work. “We’ve made some progress.”

The fire broke out on the bridge over the Monongahela River about 1 p.m. Sept. 2 after a worker cutting steel ignited a plastic pipe and tarp near the 30-foot-long chord. The bridge was undergoing an $80 million repair job by Joseph B. Fay Co. that began in March.

Pittsburgh firefighters put out the blaze, which burned at temperatures of more than 1,200 degrees, in about a half hour, and no one was injured. The bridge, however, has been closed to traffic ever since.

The closure has caused traffic tie-ups throughout the city and forced the Pittsburgh Public Schools to adjust start times at seven of its schools. The school district announced Friday that four of those schools — Allderdice High School, Milliones 6-12, Obama 6-12 and Westinghouse 6-12 — will return to their normal start times Monday.

PennDOT officials said shortly after the fire that damage to the beam was so significant that the bridge was at risk of collapsing. Because of that possibility, PennDOT is monitoring the bridge around the clock.

Advertise with us

“There is inherent risk any time that you’re attempting to move a major river bridge, but there was considerable effort put into the development of this jacking procedure to mitigate that risk,” Mr. Cessna said. “If we felt it was unsafe, we would not have all of our employees up on that bridge.”

Mr. Cessna could not predict how long the jacking process will take, but he said when it is finished officials should have a more clear outlook on when the bridge might reopen.

“At that point you are finalizing the 3-D model and the load redistribution, and then understanding whether the bridge can be reopened at the full capacity that it had prior to this issue or whether we would open the bridge with a weight restriction,” he said. “So that would be the next process, and then ultimately testing the bridge and reopening it.”