Mortar repairs and facade cleaning on one side of the nearly century-old City-County Building started this week — one project in Pittsburgh’s $4.5 million plan to update its facilities this year.

By the time the work is completed in July, the side of the Downtown building facing Grant Street will again feature two flagpoles, as was intended in the original design of the building, which opened in 1917, said Guy Costa, the city’s chief operations officer.

“When it’s done, the building will look like it did when it was constructed,” he said.

Deteriorated mortar between the building’s granite stones led to leaks in offices throughout the building, which serves as city hall and houses courtrooms and county offices.

Advertise with us

The sidewalk along Grant Street will be open during the day, but may close in the evening when the stone is chemically cleaned. Scaffolding went up Thursday to protect pedestrians.

Two 20-foot flag poles will extend over the Grant Street sidewalk from between the fifth and sixth floors of the building, said Cas Pellegrini, the city’s architectural project manager.

Several years ago, loose and cracking stones in the decorative parapets and cornices around the top of the building were addressed in an emergency repair at a cost of $4.3 million.

“This is an old building. It’s really suffered some masonry deterioration over the years,” Mr. Pellegrini said.

Maintenance costs of the building are split between the city and county, with Pittsburgh responsible for the Fourth Avenue and Grant Street facades and Allegheny County in charge of the sides facing Forbes Avenue and Ross Street.

Advertise with us

Mr. Pellegrini said the city will consider work on the Fourth Avenue side next year.

“We can't eat this whole elephant right now. We have to take it one bite at at time. This building has neglected for decades, and we have to take care of it step by step,” Mr. Pellegrini said.

In Pittsburgh’s $70 million capital budget for 2016, $4.5 million was allocated for facility improvements, of which $500,000 was earmarked for the facade project. The city also set aside another $285,000 for additional work at the City-County Building, including roof and elevator repairs.

The facility improvement budget also accounts for a 40-year facilities optimization plan by Massaro Construction Management Services not to exceed $1 million.

“We were just scrambling to stop the bleeding. Now, we’re moving toward a more proactive and budgeted approach to taking care of and maintaining our facilities,” Mr. Pellegrini said.

Advertise with us

The consultant, architects and engineers will visit each of the city’s nearly 300 buildings to asses their needs.

“Rather than waiting for something to fail, we will know what’s good, what’s bad and what’s ugly, and then we can put it into the budget,” Mr. Pellegrini said.

Lexi Belculfine: lbelculfine@post-gazette.com or 412-263-1878. Twitter: @LexiBelc.