After a four-month delay for redesign of a construction project, traffic on Smithfield Street in Downtown, beginning today, will be limited to Port Authority buses between Fourth and Fifth avenues while the intersection at Forbes Avenue is rebuilt.

A. Merante Contracting Inc. was scheduled to begin the project in mid-October. But when workers opened the street to extend a new sewer line from Forbes Avenue to Smithfield, they unexpectedly ran into an underground Verizon telephone line, said Kenneth Olup, overseeing the project for Pittsburgh as a project manager for Hill International.

Instead of moving the Verizon line, Mr. Olup said, engineers redesigned the sewer extension to tie in at a different location on Smithfield. Redesigning the work and getting approval from the Pittsburgh Water and Sewer Authority held up the work.

The work is part of a $5.3 million project to rebuild Forbes between Smithfield and Wood Street, which has 80 percent state and federal funding. Hill International is involved because the project is an extension of work that started with rebuilding the section of Forbes between Wood Street and Market Square.

Advertise with us

Contractors have run into similar problems with unexpected utility structures deep underground throughout the project, Mr. Olup said.

As a result of the project, one bus lane toward the Smithfield Street Bridge will be the only traffic on Smithfield between Fourth and Fifth avenues. Traffic on Forbes will be detoured at Cherry Way for at least the first month of the project, but one lane may be open after that, Mr. Olup said.

Although the traffic restrictions will be all day, Mr. Olup said, the redesign will result in a lot of the work being done overnight to avoid bus traffic. This is for the safety of workers because the location of the new sewer connection is closer to the lane of traffic.

Ed Blazina: eblazina@post-gazette.com or 412-263-1470.