From its space on East North Avenue on the North Side, the Light of Life Rescue Mission has served as a beacon of hope for homeless men, the hungry, and those struggling with addictions.
Now the organization is taking the first steps toward the eventual closing of the facility and the relocation of its services to other parts of the neighborhood, including a new building on Madison Avenue.
It is negotiating with the city Urban Redevelopment Authority to buy 18,800 square feet of URA-owned vacant lots on Madison and Voeghtly Street near Interstates 279 and 579 for the new facility. URA board members authorized 90 days of exclusive negotiations this week.
Craig Schweiger, executive director of Light of Life Ministries, said the proposed 15,000-square-foot Madison Avenue facility would serve two of the mission’s core ministries for the poor and homeless — daily meals and shelter beds for men, women, and families.
One advantage in building the three-floor facility is that it will allow the organization to serve all meals at one time, rather than in phases, as it is forced to do now.
Light of Life also is planning to shift its administrative staff and its programming for men recovering from drug and alcohol abuse and the chronically mentally ill to an old school it owns on Ridge Avenue. The building also will provide shelter beds and meals, but not the daily meal ministry.
The 45,000-square-foot Ridge Avenue facility will serve as Light of Life’s main site, while Madison will be a satellite location. Mr. Schweiger said one of the goals is to spread Light of Life services between the two facilities to help minimize negative impacts to the community.
Once the moves have been made, Light of Life plans to sell the 20,000-square-foot East North Avenue building it purchased in 1979 for development purposes.
Light of Life intends to relocate in two phases. The first will be acquiring the land on Madison and Voeghtly for the new facility, followed by the move to Ridge.
Mr. Schweiger estimated the cost of the new building at $3 million and the renovations required at Ridge at $7 million. “It needs a lot,” he said of the latter.
Light of Life expects to break ground on the new building by summer and have it completed in roughly a year, Mr. Schweiger said. It hopes to start work on renovations to the Ridge Avenue building in 2017, but that depends on fundraising efforts.
The plans for the new building and the Ridge relocation have the support of the Northside Leadership Conference, said Mark Fatla, executive director.
In a lot of cases, the relocation of the kind of services provided by Light of Life might evoke vows of “not in my backyard or even worse, no way in hell,” Mr. Fatla said.
But North Side leaders have taken a different approach and worked with the nonprofit Christian mission to find viable alternatives, he said.
The administration of Mayor Bill Peduto also has embraced the proposal, said Kevin Acklin, his chief of staff and chairman of the URA board. The new building would allow the organization “to fulfill its mission and meet people where they are,” he said.
“You’re truly doing God’s work with that mission,” Mr. Acklin said. “I really think this is a good thing for the community.”