Pittsburgh Mayor Bill Peduto said Thursday there’s been “a lot of positive movement” in altering the design of the new U.S. Steel headquarters to satisfy him and other critics.

After meeting with representatives of Clayco Realty Group, the project developer, Mr. Peduto said that efforts to craft a design satisfactory to everyone are progressing.

“Clayco has been working hard to be able to recognize what can be done in order to really have a quality building that reflects not only what U.S. Steel will need but also what the site will need for future development of high-quality standards,” he said.

Mr. Peduto said he agreed with criticism leveled last week by Christine Mondor, city planning commission chairwoman, who likened the building to one found in a suburban office park. She was concerned it did not make a bold enough statement for U.S. Steel or for the site on which it will be developed.

Advertise with us

The headquarters will be the first building to be built on the 28-acre former Civic Arena property in the lower Hill District, where the Penguins are proposing a mix of offices, residences and entertainment. The hockey team holds the development rights to the publicly owned land.

Mr. Peduto said the U.S. Steel headquarters “does set the bar” for future development and “we wanted to make sure that Clayco understood the responsibility that they have of making sure that quality design follows.”

He noted his suggestions for improving the design involved changes along the roof line, the “breaking up of the building,” and the materials being used “in sort of creating instead of a monolithic structure one that was more in line with what Pittsburgh’s architecture is more like, the urban fabric of the architecture.”

“We’ve worked very hard to make sure U.S. Steel stays in Pittsburgh and our commitment has been to U.S. Steel that we will make this process as seamless as possible. But at the same time, we have to assure the quality of the design for the first building that goes in is setting the bar for others,” he said.

Robert Clark, Clayco CEO, said after the meeting “good refinements” were being made to address the concerns. The firm will present the design changes at Tuesday’s planning commission meeting.

Advertise with us

“We’re hearing the mayor loud and clear and we’re listening to the planning commission,” he said. “We’re refining the design both in the context of what U.S. Steel’s needs are and what the city is pushing very hard for.”

While Mr. Clark was not specific in the types of changes being contemplated, representatives of Clayco said at a meeting in the Hill on Tuesday that the five-story building’s long, smooth face would be broken up and the main entrance would be more clearly defined.

The developer has said that U.S. Steel has set a limit on what it wants to spend on the project and that additional costs related to the design have to be weighed against that. The building cost has not been divulged.

Clayco hopes to start construction of the 285,000-square-foot building in the fall and have it completed by fall 2017 before the steelmaker’s lease expires in its current headquarters at U.S. Steel Tower, Downtown.