Completion of the Parkway East bridge over Business Route 22 in Monroeville will conclude six seasons of construction that rehabilitated one of the region's busiest highways from end to end.
But there won't be much of a break for parkway drivers, as the Pennsylvania Department of Transportation plans to start a three-year rehabilitation of the Squirrel Hill Tunnels in March.
The $50 million to $60 million project will literally raise the roof of the tunnels, through which nearly 49,000 vehicles pass on an average day. PennDOT is hoping that, and brighter lighting, will ease the chronic backups there.
Project manager Guy Rettura said removal of a drop ceiling in the tunnels will add about a foot to the current 13-foot, 6-inch vertical clearance, reducing the number of overheight trucks that have to be turned around at the entrance. It also will expose an arched ceiling similar to that of the Liberty Tunnels, he said.
The project also calls for cleaning and repointing the facades, upgrading ventilation, safety systems and computer controls, and improving two nearby bridges, on Commercial Street and the Swissvale interchange ramp over Braddock Avenue.
No lane restrictions or closures will occur during peak traffic times, but the contractor will be allowed to close the tunnels in one direction on eight weekends between March 16 and Nov. 14, 2012, and eight more in 2013. Single-lane closures will occur at night.
"It's clearly going to have a major impact on traffic," PennDOT spokesman Jim Struzzi said. "We'll do everything we can to give advance notice of closures."
Drivers can subscribe to construction alerts and updates by emailing him at jstruzzi@pa.gov with "Parkway East-subscribe" in the subject line.
The project schedule, which is subject to change, calls for completion of the project in July 2014. It is possible that an aggressive contractor could finish sooner, said Cheryl Moon-Sirianni, PennDOT assistant district executive for design.
The tunnels, eight-tenths of a mile long, were opened to traffic in 1953 and have become notorious for backups that can occur at all hours of the day.
PennDOT is hoping the higher ceiling and brighter lights will encourage drivers to maintain their speed as they approach. Officials say the jams are caused primarily by motorists hitting the brakes, causing others behind them to do likewise.
Parkway drivers have endured major construction every year since 2006 as PennDOT has invested more than $110 million in resurfacing, bridge improvements and other upgrades.
This year, in addition to the bridge work in Monroeville, PennDOT spent $3.2 million smoothing out rough pavement transitions at several bridges.