On the day a portion of Becks Run Road was supposed to reopen after a months-long construction project, Pennsylvania American Water said Friday the closure would extend into November.

"Probably we were optimistic we were going to be able to meet that 9/30 date and get two lanes of traffic opened up," said Jay Lucas, the utility's project manager. But last week "it became obvious that wasn't going to happen."

During the remainder of the $101 million project drivers can still head outbound -- from East Carson Street toward Wagner Avenue in Carrick -- on Becks Run. But motorists headed in the opposite direction will have to detour at Wagner.

Pennsylvania American Water blamed rainy weather and unexpected obstacles under ground for lengthening the project. The former delayed pouring a concrete sub-base to repave the road, and the latter led to digging up more roadway than was anticipated.

Advertise with us

The company is replacing its water intake on the Monongahela River, which draws up to 60 million gallons per day, along with a 117-year-old pump station, 2,900 feet of underground main and the Hays Mine Water Treatment Plant.

Detours are posted.

For more information about the closures or other portions of this project customers can contact Pennsylvania American's contractor, Kokosing Construction Inc., at 1-877-856-3030.