Pittsburgh police officers who have been directing traffic near the off-ramps from the Veterans Bridge, Downtown, during construction were not there this morning, resulting in a major traffic backup.

One driver reported it took 40 minutes to travel one mile on the bridge to reach the off-ramps and another said traffic backed well up the Parkway North.

A spokeswoman at the police special events office said a PennDOT contractor neglected to place an order for the extra officers. "It was an error on their part. They have to order officers," said the spokeswoman, who declined to be identified. She said the situation has been rectified and officers will be stationed at the intersections this afternoon and for the remainder of the week.

"There was some miscommunication in scheduling the officers," PennDOT spokesman Jim Struzzi said. He said he did not have details but said the problem has been remedied.

Advertise with us

The officers were put in place after a traffic jam July 11, the first rush hour after PennDOT closed two bridges over the Crosstown Boulevard as part of an $18.7 million rehabilitation project.

Things weren't much better for drivers going the other way on the Veterans Bridge. A minivan stalled in the Route 28 construction zone just before the 31st Street Bridge, blocking the only northbound lane and causing traffic to back up onto the Veterans and Fort Duquesne bridges. It took more than an hour for a tow truck to reach the scene.