An extended season of disruption for motorists who use the Liberty Bridge begins this weekend and will be concentrated on the Uptown end of the bridge.

During this construction season, the Pennsylvania Department of Transportation’s $80 million bridge rehabilitation project will feature an extended closure of the Boulevard of the Allies near Downtown; up to 11 overnight closures and 11 weekend full bridge closures; single-lane restrictions on Second Avenue beneath the bridge; and short-term overnight closures on the Parkway East beneath the bridge.

Preparations for the project’s second year begin at 6 p.m. Saturday, when contractor Joseph B. Fay Co. closes the bridge in both directions; the Liberty Tunnel inbound; and the ramps from the bridge to the Boulevard of the Allies, which will remain closed for 80 days for bridge wing reconstruction, stringer erection and grid deck installation.

The bridge and tunnel will reopen inbound from 2 to 5 p.m. Sunday to accommodate traffic for the Pittsburgh Penguins’ 5 p.m. game, then close again until 5 a.m. Monday. Two outbound lanes on the bridge will reopen at 5 p.m. Sunday and remain open until 5 a.m. Monday.

Advertise with us

The outbound tunnel will remain open all weekend and motorists will be able to use McArdle Roadway and Arlington Avenue.

Another restriction begins at 6 a.m. Monday, when the Boulevard of the Allies also will close for 80 days between Grant Street and the Liberty Bridge for deck reconstruction, steel repairs and painting operations.

Weekday lane restrictions on the bridge also resume in late April with the same pattern as last year: Two inbound lanes and one outbound will be open from 5 a.m. to 2 p.m.; one inbound and two outbound lanes from 2 to 7 p.m.; and one lane in each direction from 7 p.m. to 5 a.m.

The full weekend bridge closures will be scheduled to allow crews to install a latex overlay on the new surface, eliminating the rough ride at joints, and to replace expansion dams.

The restrictions on Second Avenue, which will last 42 days, and the Parkway East will allow workers to paint the bridge and make steel and deck repairs.

Advertise with us

They haven’t been scheduled yet.

Sidewalks on the bridge will remain closed.

Ed Blazina: eblazina@post-gazette.com or 412-263-1470.

Correction (made April 5, 2017, at 11 a.m.): Lane changes due to construction on the Liberty Bridge won’t begin until late April. An earlier version of this story had incorrect information.