After over a year of closure for maintenance, the Steel Curtain roller coaster is finally reopening to Kennywood visitors.
The marquee coaster previously shut down in April 2024 for an “extensive modification project,” the West Mifflin park’s general manager Ricky Spicuzza said at the time.
A little over a year later, the ride will reopen for thrill-seekers at 11 a.m. May 24 with a ribbon cutting ceremony attended by current and former Pittsburgh Steelers, Mr. Spicuzza said. Gold and Platinum pass holders should have an opportunity to ride the coaster even earlier, but a specific date has not yet been released.
The Steel Curtain, with its maximum height of 220 feet and nine inversions, originally opened in 2019. Since then it’s faced numerous closures, including one in July 2023 that lasted the rest of the year after park employees noticed excess structural movement occurring as trains rolled along the track, Mr. Spicuzza said.
That’s why Kennywood decided to shut the coaster down for the entire 2024 season, he explained. After the park completed a technical inspection of the Steel Curtain through the ride’s manufacturer and multiple third parties that April, it decided a modification project was necessary for the ride’s columns, towers and supports. Park officials hoped to decrease movement and increase longevity.
“It’s important to keep in mind that, while the movement of the ride was accounted for in the initial design of the coaster over time, we looked at that and we could see that the movement could cause additional wear and tear,” Mr. Spicuzza said. “So we wanted to be preventative and proactive. And what that does is it gives us that longevity to make sure the ride is here for a long time.”
Read More
Some structural movement is “completely normal,” Mr. Spicuzza said, assuring that the coaster was built with strict standards and was always safe for riders when open.
Drawing from conversations with the park’s internal engineers, Kennywood director of communications Lynsey Winters compared the potential wearing process to that of a paper clip.
“If you take a paper clip and you keep bending it and bending it and bending it, you can put it back, but it’s never going to be the same again in the place that you kept bending it and moving it,” Ms. Winters said.

With the modification portion of the project complete, three of the Steel Curtain’s main towers now feature new columns that add structural support alongside various braces and crossmembers, Mr. Spicuzza said.
Park-goers can determine which supports are new based on the number of bolts used to secure them, Mr. Spicuzza added; newer columns have more bolts than the older ones.
“That’s the only thing that was changed during the project. Everything else, the track, the ride, is going to be the same,” he said.
Still, there are a few steps left in the process.
Those steps include “hundreds” of test runs to ensure the ride is working properly, another full inspection by both Kennywood and a third party company, and a final inspection by the Pennsylvania Department of Agriculture’s Amusement Ride Safety Program, which will make a final determination on the May 24 reopening.
The roller coaster will also have less “technical downtime” than it experienced before the modification project, according to Mr. Spicuzza, who believes that notion will lead to an increased amount of ridership for visitors.
In conjunction with the modifications, Kennywood revealed a new logo for the Steel Curtain in early April that features the ride’s name in a bold font with black-and-gold to give the coaster a “refresh” and help celebrate its “grand return.”
“There’s a lot of excitement in Pittsburgh, but I think there’s a lot of excitement really through the U.S. and the industry on this ride because it’s a phenomenal ride,” he said. “We’re just beyond excited to have that back.”