Work to finish a 2 1/2-mile segment of the Great Allegheny Passage trail in the Mon Valley will begin soon, with a projected mid-June opening.

That is one of several improvement projects that are advancing along the region's trail network.

Linda McKenna Boxx, president of the Allegheny Trail Alliance, said a construction contract has been finalized with Murin and Murn Inc. of Glassport to pave a 2,700-foot section starting at Grant Avenue in Duquesne.

That will open up the trail section where two bridges were erected last summer -- a 110-foot-long span in the RIDC industrial park in Duquesne that crosses three sets of Norfolk Southern Railway tracks and a 170-foot-long bridge in Whitaker over six sets of tracks operated by Norfolk Southern and Union Railroad Co.

Advertise with us

The new section will go as far as The Waterfront, ending at the final missing link in 335 miles of trail between Pittsburgh and Washington, D.C. Planners are targeting Nov. 11 for opening the nearly one-mile section through Sandcastle Waterpark and an adjacent scrap yard.

"We have a long way to go in fundraising," Ms. Boxx said of the estimated $3.1 million that will be needed to complete the Sandcastle segment.

Toole Design Group of Washington, D.C., has been selected to do conceptual plans for the segment. Some utility relocation work may occur before the waterpark opens for the season, then any additional construction will be on hold until the park closes for the year, she said.

State Sen. Jay Costa Jr., D-Forest Hills, in December announced a $750,000 grant toward the project, to be matched with $500,000 from Allegheny County and $1 million in private donations.

The state money hasn't been released, but Ms. Boxx said trustees of the Katherine Mabis McKenna Foundation of Latrobe has pledged $500,000. She is chairwoman of the foundation.

Advertise with us

"I can't guarantee it," she said of the Nov. 11 target date, "11-11-11," which county Executive Dan Onorato has touted for completing the last link.

In other trail news, work is expected this spring on the North Shore to resurface the rutted sections on either side of the new concrete trail structure near the 31st Street Bridge. The structure was built to move the trail as close to the Allegheny River as possible to make way for the Route 28 project.

"We hope to have contracts signed in a couple weeks," said Thomas Baxter, executive director of Friends of the Riverfront. Landscaping also will be done in the area.

Work is continuing on a $1.1 million Montour Trail bridge crossing Clifton Road in Bethel Park.

Abutments have been placed for the J.R. Taylor Memorial Bridge, named for the late superintendent of Century Steel Erectors. The company and Mr. Taylor's family have worked to raise money for the bridge since Mr. Taylor died in an accident in 2004 while doing yard work.

Advertise with us

The bridge will complete the 2.7-mile Bethel Park branch of the trail, which stretches from the Arrowhead Trail in Peters to Irishtown and Logan roads in Bethel Park.

Steel will be delivered to the site in June, and bridge erection is scheduled for mid-July. It will require a two-week closure of Clifton Road while the steel structure is assembled and lifted into place, said Ned Williams, president of the Montour Trail Council.

If the schedule holds, the bridge could open to traffic in late August or early September, he said.

Construction of a new 3- to 4-mile Montour Trail spur in Washington County could begin in late summer, Mr. Williams said.

A natural gas company, MarkWest Energy Partners of Denver, has agreed to build the spur in Cecil, Mount Pleasant and Chartiers, in exchange for using trail council land for a rail line connecting its processing plant near Houston, Pa., with the Wheeling & Lake Erie Railroad.

Advertise with us

The new segment will intersect the trail main line at Gilmore Junction, near Southview Road and Route 50 in Cecil. It likely will not open until next year.

Construction may begin in the fall on bridges to cross trail gaps at Georgetown Road and Morganza Road in Cecil, Mr. Williams said.

Also, engineering work is proceeding on a planned bridge over Brush Run that, when built, will spare trail users having to negotiate a 700-foot stretch of Valley Brook Road in Peters. No construction is likely this year.