Anglers and boaters may have to wait longer than expected for the Riverfront Park boat launch on the South Side to reopen.
May 31 is the target date for completion of a larger launch ramp, handicap accessible fishing pier and three floating docks. But a problem involving the placement of pilings for the docks may cause the city to miss that deadline, city of Pittsburgh project architect Al Kovacik said Friday.
Crews have been under pressure to finish the launch work by June. That's when contenders in the CITGO Bassmaster Classic are allowed to practice-fish tournament waters. Local boaters are growing impatient, and some anglers have been sneaking past construction fencing to fish the Monongahela River from the shore, much to the dismay of workers who thought their biggest annoyance was going to be nuisance geese.
"The public's clamoring to get in there," Kovacik said. "But when the pilings are not in the correct place, you've got a problem. The docks won't fit. They'll have to be re-configured so they do fit properly. That will require custom fabrication, which is normally a five to eight week process. We can't guarantee when that'll be done, so the end of May might not happen."
Though flooding earlier this spring caused damage to the new fishing pier, Kovacik said the city didn't lose much construction time because mild weather this past winter had enabled crews to make progress on the toughest part of the job -- pouring concrete.
Until the pilings and dock problem surfaced, all that remained to be done was replace some asphalt, install a gangway from the shore to the docks and landscape, Kovacik said. A pavilion had been part of the original plans, but was scrapped because of a lack of funding.
How much overrun the piling and dock snafu will cause, Kovacik couldn't say. The Pennsylvania Fish and Boat Commission is using federal funds to pick up half of the $200,000 cost, while Pennsylvania Department of Conservation and Natural Resources secretary Michael DiBerardinis was in town last Wednesday to present a check for the other half, as part of his stump for Growing Greener.
Although the launch will be able to accommodate three boats at a time -- which will come in handy during the Classic -- Kovacik said two boats at a time is the more practical expectation and a big improvement over the past. In addition, he said, tie-ups will be located downstream, out of the way, which also should hasten the launch process and, he hopes, the bottlenecking that occurs on the road leading to the launch on busy days.