On a stifling day a month ago, Point Breeze businessman Lee Brown and members of the fledgling Greater Pittsburgh chapter of the Izaak Walton League of America took a walking tour of the $7.7 million restoration project that began three years ago on Nine Mile Run in Frick Park.
Darrell Sapp, Post-Gazette
The restoration project for of Nine Mile Run, shown here near Braddock Avenue and the Parkway East, was started three years ago.
Click photo for larger image.
Related article:
IWLA welcomes Pittsburgh chapter
The sulfurous stench of the Monongahela River tributary, so-named because it is 9 miles from Point State Park, hung in the hot air but did not daunt Brown and his fellow outdoorsmen, who are eager to adopt the evolving stream. Much tougher to take is news the U.S. Army Corps of Engineers has run out of funding for the project, at least until October or whenever Congress passes the federal budget for the new fiscal year.
This year's $400,000 is far short of the $1.6 million originally promised, said USACE project manager Lenna Hawkins, and how much Congress will ultimately approve for the $3.4 million needed to finish the project is "anybody's guess," Hawkins said. If all that comes through next year is another $400,000, the project could drag on for five more years, instead of the two originally planned, she said. The project is just a quarter of the way completed.
"I hate to say this, but if they go with a five-year model, it could result in the stream restoration not getting done," said Marijke Hecht, executive director of the Nine Mile Run Watershed Association, created three years ago to engage citizens, such as Brown, in eco-stewardship activities. "It'll certainly leave us in worse straits. If a big chunk of the money is used to remobilize and demobilize construction crews every time there's a funding issue, it'll eat away at money for the actual restoration, because you can't expect the contractor to absorb those costs."
Meadville Land Services has told Hawkins it will halt operations within four weeks, leaving some of the 6 1/2-mile watershed cleared of invasive plant species vulnerable to re-growth. It also will put partially excavated stream channels for a reconfigured Nile Mile Run and its two main feeder streams, Fern Hollow and Falls Ravine, at risk for erosion and sedimentation. Fern Hollow begins at the Homewood Cemetery but picks up speed in Frick Park. Falls Ravine's headwaters are near the Frick Environmental Center.
The Meadville-based company was set to begin establishing wetlands with willow, sycamore and other native flood plain trees, witch hazel and other shrubbery, and native plants such as coneflower and swamp milkweed. But the funding crisis has put those plans on hold.
"Meadville thinks it can put in some native grasses as a stopgap to try to halt erosion, otherwise we're in big trouble," said Hecht, who, until last week's news from the USACE, thought the project's biggest nemesis was this year's heavy rains.
Rain always has been an issue with Nine Mile Run, since storm events wash waste from neighboring communities through substandard sewers into the stream and erode its banks, beginning where it sees daylight, below Braddock Avenue in Regent Square. It will help Nine Mile Run that municipalities within the watershed are making sewer improvements. In the wake of the funding crisis, that strikes Hecht as ironic.
"The feds are mandating that these tiny municipalities comply but aren't holding up their end of the bargain," she said.
Plans call for meandering the 2.2-mile stream, that joins the Monongahela River in Duck Hollow, to create a sequence of riffles and pools ideal for sustaining aquatic life. Limestone boulders piled off Commercial Road below the Parkway East will be used to install a series of step pools in the stream and its two tributaries. Though it may be a decade before stocked trout are rising there, Nine Mile Run is the sort of urban water the Pennsylvania Fish and Boat Commission sees as the future of fishing because it is accessible to so many people and on un-posted land.
It is a dream shared by Brown and others eager to acquaint city residents with the green space in their own back yards.
"We want to step forward and help out because we use Frick Park, and our children and our children's children are going to use it," said Brown, who looked beyond the beer cans strewn on the stream banks to marvel at signs of turkey and deer that live in the park.
"That's 100 years of awful," said Brown of the sewage odor on the stream. "But there will be trout in here one day as long as we, the neighbors, take care of it."
Hecht is looking to groups such as Brown's to steward Nine Mile Run, by cleaning litter, monitoring and managing evasive species and fostering awareness. Getting folks excited about Nine Mile Run is part of the watershed association's mission, along with a rain barrel initiative, street tree planting, the greening of vacant lots and other improvements within the Nine Mile Run community.
Though they are funded independent of the stream restoration, they are part of the same picture. The watershed association, which conducts bi-monthly walking tours of the project, has scheduled a special "lack of restoration" tour for 10 a.m. on Aug. 14 to call attention to the funding crisis. It begins at the Falls Ravine Shelter in Frick Park.
For more information visit, www.ninemilerun.org or call, 412-371-8779.
This story was originally published with images that are no longer available.