GE Vernova is doubling its footprint in southwestern Pennsylvania, where the company has two factories and a third slated to start production of in-demand electric equipment next year, and adding 700 jobs in the next few years.
The company has about 1,200 employees in the state, most of them in the Pittsburgh region, a spokesperson said.
Each Monday morning, about a dozen new workers punch their time cards for the first time at the company’s Charleroi facility, its chief corporate officer Roger Martella said on Thursday, standing alongside those workers who make high-voltage electrical equipment there.
“The grid is the most complicated machine anybody's ever built, and they're building the most important equipment that makes the grid work and that's going to make it work better,” Martella said.
GE Vernova is building out its new manufacturing space in Rostraver. In March, the company spent $70 million to buy a 700,000-square-foot warehouse in Rostraver, where it had previously been leasing space, and is currently preparing that space for production of similar kinds of circuit breakers that are currently being made in Charleroi.
At its third facility in Findlay, GE Vernova makes inverters for solar and battery storage equipment.
All three are part of GE’s growing electrification business segment, which serves anyone that needs to move power from one place to another — think utilities, transmission operators, industrial consumers and, yes, data centers.
“We are in the early stages of this electricity investment supercycle,” the company’s CEO Scott Strazik told investors during an earnings call earlier this month in which he talked about expansion in Pennsylvania.
The momentum is coming from historically high demand for equipment that makes and transmits power. GE Vernova makes both. Data center developers and utilities are lining up for natural gas turbines, which now have a five-year waiting period.
Last year, GE Vernova announced it will be supplying the gas turbines to power the redeveloped Homer City project, slated to produce twice as much power as the demolished coal station that once bore that name. (Those turbines are not made in southwestern Pennsylvania.)
Moving electrons around requires equipment that can adjust voltage and interrupt current when needed. To harness renewable energy, you need inverters. Those things are made in the Pittsburgh region.
Mass.-based GE Vernova has 85,000 employees globally and more than 90 manufacturing sites. But on Thursday, its CEO joined Pennsylvania Gov. Josh Shapiro on the shop floor in Charleroi for an overview of its plans for the Keystone State.
Starting the ramp up early last year, Strazik said the company is slated to invest more than $200 million in southwestern Pennsylvania, creating 700 new jobs.
“And we're going to keep building on it from here,” he said.






Comments