Friday, July 04, 2025, 8:53AM | 
MENU
Advertisement
The site of a natural gas pipeline explosion seen here on Thursday, Oct. 18, 2018, in Center Twp. The Revolution pipeline, 24-inch line owned by Energy Transfer Corp., exploded on Sept. 10, 2018.
1
MORE

Pa. DEP orders Energy Transfer to fix damage to streams and wetlands

Andrew Rush/Post-Gazette

Pa. DEP orders Energy Transfer to fix damage to streams and wetlands

Twenty-three streams that flowed through southwestern Pennsylvania before Energy Transfer built its Revolution pipeline have been filled with dirt. Seventeen wetlands no longer exist because of the 40-mile line, whose explosion in Center Township last September has brought even more scrutiny to the pipeline company that is already among the most investigated in the state.

The early morning blast, caused by a landslide, has been followed by months of continuing violations of state laws meant to protect streams and wetlands.

A month after the explosion, the Pennsylvania Department of Environmental Protection ordered Texas-based Energy Transfer to stop trying to repair the pipeline and focus instead on stabilizing the nearby ground. DEP also told the company to survey what damage it might have done to water resources along the path of the natural gas gathering line.

Advertisement

Those findings — submitted in February — provided the foundation for the DEP’s new order issued on Monday, setting a timeline for Energy Transfer to do a more comprehensive search for unpermitted damage to water resources and to come up with a plan to repair that damage.

A view of the burned out hillside below Ivy Lane after a gas line explosion, Monday, Sept. 10, 2018, in Center Township.
Kris Mamula and Anya Litvak
Officials believe landslide may have triggered massive gas pipeline explosion in Beaver County

According to the February report, Energy Transfer filled in 23 streams, about a dozen of which flowed into Raccoon Creek.

It piled soil and dirt into portions of other streams, eliminating a total of 3,100 feet of streams along its right of way. The company also altered 70 wetlands, in addition to the 17 that were eliminated.

The construction process caused 31 new wetlands and eight new streams to form. 

Advertisement

“The water that was flowing or being stored in these [altered] streams and wetlands had to go somewhere else,” explained DEP spokesman Elizabeth Rementer. “The erosional forces of the water basically carved out new stream channels.”

Earth-moving activities such as laying pipelines do disturb some natural features, although “pipeline projects do not typically eliminate streams and wetlands,” Ms. Rementer said. 

“Any proposals to do so would have to be set forth in permit applications with appropriate justification.”

The streams and wetlands that were part of Monday’s order exist outside of the permitting process. The DEP called them “illegal.”

The path of an Energy Transfer Corp. pipeline can be seen in this photo taken on Saturday, January 12, 2019, in Center. The pipeline was involved in a massive explosion on Sept. 10, 2018 that officials believe was caused by a landslide.
Anya Litvak
State DEP says company not complying with order after Beaver County pipeline blast

Energy Transfer has until July 30 to complete a full survey of impacted water resources, another month to come up with a plan for restoration, and until Sept. 30 to file any permits needed to carry out the plan.

For water features that can’t be brought back, the DEP wants the company to replace them at a ratio of 4 to 1.

The Revolution Pipeline was built to collect natural gas from wells and carry it through Butler, Beaver, Allegheny and Washington counties to an Energy Transfer processing plant. It was put into service a week before the explosion. 

Anya Litvak: alitvak@post-gazette.com or 412-263-1455.

First Published: May 14, 2019, 9:34 p.m.

RELATED
Photo taken during a Department of Environmental Protection inspection of Energy Transfer's Revolution pipeline on Jan. 24 showed continued erosion and unstable ground five months after a pipeline explosion in Center Township, Beaver County.
Laura Legere
DEP halts permit reviews on major Pennsylvania pipeline projects
The path of a new, 12-inch natural gas pipeline being built by National Fuel crosses Energy Transfer's Revolution pipeline behind the house with the red roof. This photo, taken in December, shows the cleared right of way for both pipelines. Energy Transfer has since purchased the red-roofed home.
Anya Litvak
'I'm surrounded.' A worried Beaver County neighborhood watches as new fuel pipelines crisscross.
Temporary erosion barriers in New Sewickley Township, Beaver County along the Revolution Pipeline in January 2019.
Anya Litvak
Beaver County agency did poor job overseeing major pipeline projects, the state found, yanking its power
The site of a natural gas pipeline explosion on Monday, Sept. 10, 2018, in Center Twp.
Anya Litvak
Energy Transfer given $30M penalty for Beaver County pipeline explosion
SHOW COMMENTS (0)  
Join the Conversation
Commenting policy | How to Report Abuse
If you would like your comment to be considered for a published letter to the editor, please send it to letters@post-gazette.com. Letters must be under 250 words and may be edited for length and clarity.
Partners
Advertisement
Pirates starter Mitch Keller pitches during the first inning against the Miami Marlins at PNC Park on June 10, 2025.
1
sports
Pirates trade talk: 5 potential partners and what they can offer in a 2025 deadline deal
Pittsburgh Police Cmdr. Shawn Malloy urged those planning to attend Fourth of July festivities on the city’s North Shore to arrive early. There is limited space and limited parking, he stressed, and roads closures could start early.
2
local
Pittsburgh Public Safety warns that changes to Fourth of July celebration will bring large crowds
Anthrocon attendees watch an interview as VisitPittsburgh and Anthrocon hosted a press conference kicking off the convention at the David L. Lawrence Convention Center Downtown on Thursday, July 3, 2025.
3
local
With its ‘very welcoming’ atmosphere, Pittsburgh again hosts thousands of furries for Anthrocon
New quarterback Aaron Rodgers throws a pass during on Tuesday, June 10, 2025, at the UPMC Rooney Sports Complex.
4
sports
Paul Zeise's mailbag: Why do the Steelers keep adding old, over-the-hill players?
Minkah Fitzpatrick waves to fans as he runs on the field before a game against the Jaguars at Acrisure Stadium on the North Shore on Sunday, Oct. 29, 2023.
5
sports
Joe Starkey: Steelers clearly won the Minkah Fitzpatrick trade — but to what end?
The site of a natural gas pipeline explosion seen here on Thursday, Oct. 18, 2018, in Center Twp. The Revolution pipeline, 24-inch line owned by Energy Transfer Corp., exploded on Sept. 10, 2018.  (Andrew Rush/Post-Gazette)
Andrew Rush/Post-Gazette
Advertisement
LATEST business
Advertisement
TOP
Email a Story