The office tower is nearly 70% finished. The live music venue and parking garage have been approved. And now the Pittsburgh Penguins are gearing up to start on the next phase of development on the former Civic Arena site — housing.
Team officials have submitted a letter of intent with the public authorities that own the 28-acre lower Hill District site, outlining plans to build about 350 residential units just below Crawford Square.
Craig Dunham, the Penguins’ senior vice president of development, said Thursday the goal is to move to secure the land needed for the work this summer and to close on it by the end of the year.
The 350 units would constitute the first phase of a broader residential development that ultimately could involve about 1,000 units on the upper part of the site.
It comes at a time when redevelopment of the land is gaining steam 16 years after the Penguins secured the development rights to it in the 2007 deal to build PPG Paints Arena.
On Thursday, officials with the team, development partner Buccini/Pollin Group, contractors and public officials celebrated the topping off of the FNB Financial Center, the 26-story office tower to be completed in early 2024 and the first construction on the site.
Read More
And last week, the Penguins got the go-ahead from the Pittsburgh Urban Redevelopment and the Sports & Exhibition authorities, the site owners, to begin the construction of a live music venue with a 4,500-person capacity and a 910-space parking garage in the next block.
The first phase of the residential will be done by the Penguins, Buccini/Pollin, and Olmec Development Company, which is headed by Bomani Howze, who also serves as vice president of development for Buccini/Pollin.
At one time, Mr. Howze was part of joint venture Intergen, a minority developer the Penguins had hired in 2018 to do the first wave of housing at the site. However, the team parted ways with that group last year.
The first section of residential will be built on part of the site bordering Centre, Bedford and Wylie avenues and Fullerton Street. The development will be multistory, most likely five floors.
“We’re obviously incredibly excited to kick off the residential because it’s a key component of any mixed-use project,” said Chris Buccini, co-president of Buccini/Pollin Group.
In line with a community benefits agreement, the Penguins are planning to designate 20% of the units as affordable to households at 60% to 80% of the area median income, Mr. Dunham said.
Under their agreement with the SEA and the URA to develop the land, the Penguins must have 10.75 acres under their control by Oct. 22 or may have to forfeit up to 40% of the revenue they generate from parking cars on parts of the site.
Kevin Acklin, Penguins president of business operations, said the team is on track to meet that threshold with the FNB, music venue and residential projects.
The move to start the housing comes as the Penguins and Buccini/Pollin are progressing steadily on the office tower, which will be anchored by First National Bank, commonly known as FNB. The complex will feature about 400,000 square feet of office space, with FNB taking about half of it, with options to expand.
While the local office market, like others across the country, has struggled because of the fallout from the COVID-19 pandemic, J.C. Pelusi, the Jones Lang LaSalle marketing director who is leasing the space, said he is talking to a lot of prospects, with “eight to 10 very serious discussions” going on.
While FNB has about 50% of the space, Mr. Pelusi said about another 5% has been leased so far, although he wouldn’t name the other tenant that has taken it.
He added he expects to have 80% to 90% of the space leased by the time the building opens.
“It fits that flight to quality. This is really the first building post COVID that’s been built with all technologies and health and wellness associated with it,” he said.
The location next to PPG Paints Arena, the new entertainment venue, and the housing also should be selling points, he said.
“It’s just going to have that vibe to it, one that corporate clients and occupiers look for for a place people want to come to work,” he said.
During Thursday’s ceremony to put the last beam in place atop the tower, officials touted the project not only as a symbol of progress at the arena site but also as a “beacon of hope” for the Hill and beyond.
Of the $110 million in contracts awarded so far, $36.7 million have gone to minority or women-owned businesses, including $25.2 million to Black-owned firms.
In addition, of the 195,000 hours worked on the site, 22% has been performed by minorities, according to statistics released Thursday by the development team.
As part of the community benefits, nearly $7.2 million in diverted tax revenues advanced by FNB will go into other parts of the Hill to help spur development. The lower Hill was destroyed and thousands of residents were displaced to build the Civic Arena in the early 1960s.
With the tower, “we are building a new model of equitable development in a country that is troubled,” said Kimberly Ellis, director of community, arts & culture for the Buccini/Pollin Group.
Beyond the FNB Tower, the music venue and the housing, the development team still has plans for two more office projects and a hotel, Mr. Buccini said.
Mark Belko: mbelko@post-gazette.com =