A proposed office, residential, and retail development on the North Shore is racking up more delays than a rain-plagued Pirates game.

Pittsburgh Stadium Authority board members Tuesday agreed to give Continental Real Estate Companies, the developer for the Steelers and the Pirates, another month until Sept. 30 to start work on Gold Lot 4 located next to the Hyatt Place Hotel.

It is the third extension that Columbus, Ohio-based Continental has received since June 2018. Without the action, the developer would have had to “take down” or buy the stadium authority-owned parcel by Friday.

Continental was given another month “to provide sufficient time” while it, the two sports teams, and the city try to work out a comprehensive agreement regarding the remaining parcels to be developed on the North Shore, said Mary Conturo, stadium authority executive director.

Advertise with us

The parties have been trying to negotiate a deal that would cover Lot 4 and Gold Lot 2 located behind the North Shore Place I and II office complex at West General Robinson Street and Chuck Noll Way.

Mayor Bill Peduto has criticized the Steelers for failing to develop the latter parcel, claiming they have been using it as “an ATM” to park cars.

Stadium Authority board chairman Stanley Lederman could not promise that the newest extension Continental has received for Lot 4, now used for parking, would be the last one.

Because of the need for city permits and planning approvals, there could be the possibility of additional extensions, he said. “But that would only be because things are going very well and we don’t want to throw a monkey wrench into anything,” he added.

Current negotiations, Mr. Lederman said, have moved quicker than past talks and are bearing fruit. “I am very enthused about this project,” he said.

Advertise with us

Barry Ford, Continental’s president of development in Pittsburgh, said he and the teams are hoping to get started on the Lot 4 work by early next spring.

“We are literally finishing up with our agreement with the stadium authority to complete Lot 4. We’re down to the final touches and anxious to get it done,” he said.

Continental is proposing an eight-story building on the lot at the corner of North Shore Drive and Mazeroski Way featuring retail, offices and up to 40 condominiums on the top floors.

In addition, the project is expected to include what Mr. Ford has described as a “really cool entertainment and retail piece” near the home plate entrance of PNC Park, a public plaza, and some type of structured parking.

The development could remove as many as 340 parking spaces currently available in Lot 4.

Advertise with us

Mr. Peduto, meanwhile, has criticized the Steelers for dragging their feet in developing Lot 2. The team gets part of the parking revenue from the lot on football game days, as do the Pirates when they play at home.

The mayor would like to see the parcel developed for housing, which has become one of his priorities for the North Shore.

In an interview last month, Mr. Peduto said Continental would get an extension to develop Lot 2, but with a firm deadline attached to it. If there is no activity by the deadline, the land would revert to the stadium authority, which would be free to hire another developer.

Under the current agreement with the authority, Continental, which was hired by the Steelers and the Pirates to develop the land between PNC Park and Heinz Field, has until May 2021 to start work on that parcel.

Mr. Ford said that “what happens on Lot 2 in the future is under discussion” as part of the agreement being crafted with the stadium authority.

Advertise with us

Lot 2 is located directly behind the Burgatory, Bar Louie, Southern Tier, and Tequila Cowboy restaurants. The Pittsburgh Post-Gazette newsroom is located in the same complex.

Mark Belko: mbelko@post-gazette.com or 412-263-1262.