Heading into the fall, local officials had high hopes that this would be the year they landed a coveted federal grant to help with the redevelopment of the former Civic Arena site.
But for the third time, it was not to be.
Despite extensive lobbying and the help of consultants, the Pittsburgh-Allegheny County Sports and Exhibition Authority was not able to secure the roughly $21 million it sought to help build a deck over the Crosstown Boulevard as part of the arena development.
The project was not one of the 39 nationwide awarded Transportation Investment Generating Economic Recovery (TIGER) grants Thursday by the U.S. Department of Transportation.
Mary Conturo, SEA executive director, said the rejection was not a fatal blow to the project, which would serve as the means to connect the former arena site and the Hill District to Downtown.
Even if the grant had been awarded, the SEA would not have been in position to start construction of the deck until the spring 2017, Ms. Conturo said. That means it still has time to secure a grant.
The SEA already intends to try again during the next round of requests for TIGER grant applications expected in the spring.
Travis Williams, chief operating officer for the Pittsburgh Penguins who hold the development rights to the arena site, said local officials have heard that the project “continues to be viewed very favorably” by DOT and Secretary Anthony Foxx.
He is confident that future rounds will produce better results.
“Based on all of the indications we’ve gotten, we feel comfortable that as we progress on the design and engineering of the cap, it will be viewed favorably in a future round,” Mr. Williams said.
This marks the third time the SEA has lost out on a TIGER grant related to the arena work.
It also had requested money to help install a street grid at the site. Last year, it sought funding for the grid and for the design of the deck, receiving a $1.55 million planning grant for the latter.
That was “a good indicator,” Mr. Williams said, that DOT has an interest in the overall project. The money enabled the SEA to proceed with the design of the deck, whose total cost is estimated at $33.5 million.
“I really feel pretty confident that when the next round comes we’re going to be successful,” said Rich Fitzgerald, county executive.
The latest application had the backing of Mr. Fitzgerald, Mayor Bill Peduto, U.S. Rep. Mike Doyle and other top local officials. The SEA also had hired three consultants at a cost of $24,500 to help prepare the grant application.
Funded primarily by a $15 million state grant, construction has started on some of the interior streets at the 28-acre arena site in anticipation of a 1,100-unit residential development and the proposed U.S. Steel headquarters, to be built near Consol Energy Center.
“The decision on TIGER does not impact either of those projects,” Mr. Williams said.
Nonetheless, news of the rejection comes a week after the Penguins paid $75,000 to get a six-month extension on buying the first parcels needed to start development. It said neither the U.S. Steel or the residential projects were ready to go at this point.
Given U.S, Steel’s recent financial woes, there has been speculation that the company is having second thoughts about building a new headquarters at the site, although Mr. Peduto has said he is confident that it will be built.
With Thursday’s awards, DOT provided $500 million for 39 transportation projects in 34 states. It had received 627 applications from 50 states and several U.S. territories totaling $10.1 billion, or 20 times the amount awarded.
Mark Belko: mbelko@post-gazette.com or 412-263-1262.