Redevelopment of the former Civic Arena site is starting in earnest this week, but it will come at a cost for those who have been parking there.

Infrastructure work will gobble up about 1,000 of the 3,200 spaces available to commuters and hockey fans, meaning that some may have to find other places to park for work or for games.

Workers already have started taking spaces out of commission by installing fencing around the portions of the site where new roads are being graded and built and utilities are being installed.

The first impact on fans will be seen tonight when the Penguins play the Philadelphia Flyers at Consol Energy Center across the street from the site. The Penguins already have alerted season-ticket holders affected by the construction that their regular spaces won’t be available and that their parking passes will be honored at other designated lots in the area.

Advertise with us

Travis Williams, the Penguins’ chief operating officer, said Tuesday that most of the fans who park at the former arena site for games are season-ticket holders. Some general admission parking also has been available in the past and will be reduced as well because of the construction.

Although the loss of the spaces may cause some inconvenience, Mr. Williams said the infrastructure work is a “great visible first sign of the development that’s starting to occur on this site.”

The parking losses, he added, are far outweighed by the potential for the proposed $440 million mixed-use development to create and save jobs and to generate tax revenue for the city and the region. “We always knew that when development occurred that parking was going to be impacted. It’s one of those things that comes along with progress and parking,” he said.

Mr. Williams noted that before the Civic Arena was razed three years ago, about 2,400 parking spaces existed at the site, only 200 more than the number that now will be available with the start of infrastructure work.

The initial impact probably won’t be as great on commuters who park in the lots. On non-event days, the lots rarely reach capacity and typically average about 2,200 parkers, Mr. Williams said.

Advertise with us

Nonetheless, more spaces will be lost when construction of the U.S. Steel headquarters starts this fall across from Consol and in the first quarter of 2016 when residential development begins near Crawford Square.

Mr. Williams said the Penguins have started talking to the city, its Urban Redevelopment Authority and the Pittsburgh-Allegheny County Sports & Exhibition Authority about replacing some of the lost parking with garages to serve fans and the development. The URA and SEA own different parts of the site.

The team has hired a consultant to determine the best locations for garages and how many spaces will be needed. Mr. Williams expects to have a better handle on future parking needs in three to six months. But he stressed that even if garages are built, they won’t replace all of the lost parking. He noted that commuters eventually may have to find spots to park Downtown or in other places or take mass transit once the site becomes fully developed.

Still, the team does hope to create enough parking to accommodate not only fans who attend games and other Consol events but the people who will be working and living on the site.

“It may be a slight inconvenience for people at this point. At the end of the day, we’re working to solve that, to make sure development happens and that people still will have a great experience when they come to Consol Energy Center,” Mr. Williams said.

Advertise with us

In all, the Penguins, who hold the development rights to the 28 acres, are planning 1,100 units of housing, 632,000 square feet of office space and 250,000 square feet of commercial space there.

The first phase of the infrastructure work that just started involves constructing part of a new road connecting Bedford and Centre avenues as well as a portion extending Wylie Avenue into the arena site. Wylie eventually will run to Washington Place. The Phase 1 work will frame the parcel on which the U.S. Steel headquarters will be built.